   1.0  | 
  
   OBJECTIVE :  | 
 ||||||||
| 
   | 
  
   | 
  
   To describe a procedure for Opening and Closing of the Quality Control
  Department.  | 
 ||||||||
| 
   | 
  
   2.0  | 
  
   SCOPE :  | 
 ||||||||
| 
   | 
  
   | 
  
   This procedure is applicable to Quality Control department at XYZ
  Company  | 
 ||||||||
| 
   | 
  
   3.0  | 
  
   RESPONSIBILITY :  | 
 ||||||||
| 
   | 
  
   | 
  
   Quality Control Chemist and above  | 
 ||||||||
| 
   | 
  
   4.0  | 
  
   ACCOUNTABILITY:  | 
 ||||||||
| 
   | 
  
   | 
  
   Quality Control Head  | 
 ||||||||
| 
   | 
  
   5.0  | 
  
   PROCEDURE :  | 
 ||||||||
| 
   | 
  
   | 
  
   Follow the following procedure for Opening and Closing of
  each department,   | 
 ||||||||
| 
   | 
  
   | 
  
   5.1  | 
  
   OPENING OF  THE DEPARTMENT:  | 
 |||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.1  | 
  
   Get issued the keys of Quality Control department from
  security department,   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   | 
  
   make signature in the register, put date and time. Only
  departmental official person is authorized to collect the key and open the
  department.      | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.2  | 
  
   Follow SOP on Entry and Exit procedure (SOP No.: ----)  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.3  | 
  
   Ensure that door lock of the department is ok.   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.4  | 
  
   Unlock the door lock and open the department.    | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.5  | 
  
   Switch on the lights in respective areas as per need.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.6  | 
  
   Check entire department for any abnormality / discrepancy (If
  found, inform   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   | 
  
   to senior / Head of the department).  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.7  | 
  
   Switch on the A/C in respective are as per need.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.8  | 
  
   Ensure proper cleaning by the sweepers in the department.   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.9  | 
  
   After checking the things are satisfactory, start the
  work.   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.1.10  | 
  
   Report
  abnormal observations if any, to Chemist/Officer or Executives.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   | 
 |||||||
| 
   | 
  
   | 
  
   5.2  | 
  
   CLOSING OF THE DEPARTMENT:  | 
 |||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.1  | 
  
   Ensure that all the workers and staff
  members leave the respective sections.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.2  | 
  
   Switch off the A/C of the respective area.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.3  | 
  
   Ensure switch off all the lights of the
  respective sections of department.   | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.4  | 
  
   Ensure that all the mains of the instruments
  except stability chambers and incubators are switch OFF.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.5  | 
  
   Ensure regulator of the LPG (Liquefied
  Petroleum Gas)is at close position.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.6  | 
  
   Ensure the control sample room is locked and
  key is deposited to department head.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.7  | 
  
   Verify the water supply of stability chamber
  is properly regulated.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.8  | 
  
   Check all water taps are closed, except
  stability chambers.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.9  | 
  
   Lock the respective section.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   5.2.10  | 
  
   Deposit the keys to security department make signature in the register and put date and time.  | 
 ||||||
| 
   | 
  
   | 
  
   | 
  
   | 
  
          | 
 ||||||
| 
   | 
  
   6.0  | 
  
    ABBREVIATIONS:  | 
 ||||||||
| 
   | 
  
   | 
  
  
  | 
 ||||||||
| 
   | 
  
   7.0  | 
  
   ANNEXURES:  NIL  | 
 ||||||||
| 
   | 
  
   | 
  
      | 
 ||||||||
| 
   | 
  
   8.0  | 
  
   SOP REFERENCES:  | 
 ||||||||
| 
   | 
  
   | 
  
    GMP guideline  | 
 ||||||||
| 
   | 
  
   | 
  
    Safety guideline  | 
 ||||||||
| 
   | 
  
   9.0  | 
  
   SOP REVISION
  HISTORY RECORD:  | 
 ||||||||
| 
   | 
  
   | 
  
  
 END OF THE SOP  | 
 ||||||||